Jobs in Lancaster






We recently installed this new bathroom. We removed the old flooring, reboarded the floor, plastered and tiled the walls and floor. We also put up a new ceiling, skimmed and painted it. Our customer trusted us to project manage the whole job, left us to it and went on holiday. Needless to say we brought the job in on time and budget and they returned to a lovely new bathroom.



We installed this new bathroom in central Lancaster. We removed the old suite, plastered all the walls and installed a new window. We over boarded the floor, installed all the plumbing and made some features out of ply which incorporated the cistern for the toilet.
We then tiled the walls and floor and fitted the suite which now included a shower cubical.
The whole job took about two weeks, both me and the customer were very happy with the end result.

We installed this Vaillant eco tec 831 condensing boiler in Ingelton in North Yorkshire. The customer wanted to free some kitchen space so we removed the old combi boiler and re-sited the new one in the loft space.
We installed a magna clean system, this removes the debris which has built up in the old radiators.
We installed thermostatic radiator valves to all the radiators and also Honeywell wireless controls. This was to ensure that the boiler was running as efficiently as possible, saving money on bills and reducing the carbon foot print of the property.
A Vaillant Eco tec 28kw we installed in Caton in the Lune Valley near Lancaster.
At this property we first had to remove the old gravity fed cylinder and tanks. We altered the pipe work leaving no unused pipes in the cylinder cupboard, installed thermostatic radiator valves and a wireless room stat ensuring that the installation complies to the energy efficiency standards.
We installed a magna clean system as the customer kept their existing radiators from the previous heating system. We also power flushed the system, ensuring maximum radiator efficiency and prolonging the life of the boiler.
We then installed and commissioned the boiler. This job took about two days to complete.